If pump should lose its balance when moving and start tripping over, never try to
sustain the pump, get away from the pump immediately.
3.4

Utility Disconnection

WARNING
WARNING
WARNING To comply with SEMI S2, install lockable shutoff devices on electrical,

3.4.1 Electrical Power - Circuit Breaker Lockout and Tagout

Lock the breaker in the OFF position and tag it out to perform maintenance or
troubleshooting.
1. Verify that the LCD display is lit (confirming that pump is powered).
2. Turn the handle of circuit breaker off and fix the lock lever of locking device.
3. Insert padlock through holes provided on locking device. Close padlock and
attach tag.
4. Keep the key with you while working. Prepare the tagout label per factory
procedures.
5. Verify that LCD display is unlit (confirming that pump is un powered).
6. If unable to confirm interruption of power via LCD display, use a voltmeter to
probe contacts at Connector CN-C. Potential between any two pins indicates
that electrical power to the pump is not interrupted.
7. The Lockout/Tagout procedures must comply with OSHA 29 CFR 1910.147 and
1910.331-335
PM10U
To avoid dangers potentially encountered during maintenance,
transportation or storage, follow instructions below to shut off
power.
Capacitors within the control panel retain residual energy after
interruption of power supply. Wait five (5) minutes after shutting
off breaker before opening the control panel. Carefully check that
bleed circuits have discharged the residual energy before servicing
the control panel.
nitrogen and cooling water supplies. These devices should be
adjacent to and within sight of the pump.