2.
Step 2 (Optional) Connect a PDU2000 cascading cable. Use a common network cable to connect
port COM1 or COM2 on the PDU2000 to the port COM1 or COM2 of another PDU2000.
----End

4.12.12.17 Connecting the NetCol5000-A020 Monitoring Cable

Prerequisites
Procedure
Step 1 Connect one end of the network cable to the J73 communications port on the side panel of the
NetCol5000-A020.
Issue Draft A (2015-06-29)
Figure 4-209 PDU2000 wiring ports
Connect the other end of the network cable to the COM port on the ECC collector.
To cascade PDU2000s, you need only to connect one of the PDU2000s to the collector.
A network cable used for monitoring is prepared.
You are familiar with the functions of all ports on the ECC collector by referring to
Introduction to ECC
Ports.
Figure 4-210
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
shows the communications port.
4 Hardware Installation
A.3
174

Advertisement

Table of Contents
loading

Table of Contents