IDS2000 Intelligent Micro-Modular Data Center
Installation Guide (2000 mm High Cabinet in Dual-Row
Aisle Containment)
Figure 4-29 PDU8000 with a tail frame
----End

4.5.5.2 Installing a 300 mm Wide Air Conditioner Adaptive Frame

Context
Procedure
Step 1 Snap the front panel of an adaptive frame between two cabinets so that the front surface of the
front panel and the cabinet door frame are on the same plane.
Step 2 Install the adaptive frame connecting plate connect the left and right side of the frame to the
cabinets.
Issue Draft A (2015-06-29)
If an odd number of 300 mm wide air conditioners are installed, the adaptive frame
needs to be installed so that the lengths of the two cabinet rows are the same.
An adaptive frame consists of a front panel, rear panel, and top panel. Perform the
following steps to install an adaptive frame.
The BOM number of an adaptive frame is 21500710.