Connecting Cables to a Busbar
When configuring two battery cabinets, install a copper busbar in one of the cabinets. Connect
the circuit breakers to the busbar after the circuit breakers are connected to the batteries.
Figure 4-191
Figure 4-191 Connecting cables to a busbar
Issue Draft A (2015-06-29)
Figure 4-190 Incorrect battery cable connection method
shows the cabling between the circuit breakers and the busbar.