Power-On Commissioning; Power-On Commissioning Process - Huawei IDS2000 Installation Manual

Intelligent micro-modular data center 2000 mm high cabinet in dual-row aisle containment
Hide thumbs Also See for IDS2000:
Table of Contents

Advertisement

IDS2000 Intelligent Micro-Modular Data Center
Installation Guide (2000 mm High Cabinet in Dual-Row
Aisle Containment)
After the installation is completed, power it on and commission it to check that all
components are intact after transportation and installation, and that the components can run
continuously, reliably, and stably.
Power on and commission starting from the input of the power supply and distribution system
to server devices or air conditioners. Devices should be powered on in sequence.

6.1 Power-on Commissioning Process

Power-on Commissioning Process
Figure 6-1
Issue Draft A (2015-06-29)
6
Before eliminating problems from upper-level devices, never power on lower-level
devices. Otherwise, severe accidents may occur.
To ensure safety, only trained and qualified personnel are allowed to power on and
commission the system.
shows the power-on commissioning process.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Power-On Commissioning

6 Power-On Commissioning
181