Figure 4-204 Cable connections of door exit buttons and access card readers
Figure 4-205
an emergency door release button (a break glass switch is configured optionally). The
following describes how to connect cables.
1.
(1) Double-door magnetic lock
(3) Four-core cable A
Issue Draft A (2015-06-29)
shows the cable connections to the electromagnetic double-swing door lock and
Pressurize and connect cables of the double door magnetic locks on the left and right
doors: Route eight cables from each of the magnetic locks, pressurize every two cables
of the same color using cold end terminals, and connect the pressurized cables to
terminal block A delivered with the device, as shown in
Figure 4-205 Cable connections of double-door magnetic lock
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
(2) Terminal block A