Installation Preparations; Transportation Precautions - Huawei IDS2000 Installation Manual

Intelligent micro-modular data center 2000 mm high cabinet in dual-row aisle containment
Hide thumbs Also See for IDS2000:
Table of Contents

Advertisement

IDS2000 Intelligent Micro-Modular Data Center
Installation Guide (2000 mm High Cabinet in Dual-Row
Aisle Containment)

2.1 Transportation Precautions

Air Conditioner Transportation Precautions
Issue Draft A (2015-06-29)
2
Only trained personnel are allowed to move the cabinet. Use a pallet truck to transport
the cabinet secured to a wooden support to the installation position. Insert the forks of
the pallet truck in the middle position to ensure balance.
Choose the rail, sea, or good road for transportation. Avoid excessive vibration or tilting
during transportation. When loading and unloading the cabinet, keep the gradient within
15 degrees, as shown in
To prevent the cabinet from falling over, secure it to a pallet truck using ropes before
moving it.
To prevent shocks or falls, move the cabinet gently.
After placing the cabinet in the installation position, unpack it and take care to prevent
scratches. Keep the cabinet steady during unpacking.
Figure 2-1 Transportation Gradient
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Installation Preparations

Figure
2-1.
2 Installation Preparations
8

Advertisement

Table of Contents
loading

Table of Contents