IDS2000 Intelligent Micro-Modular Data Center
Installation Guide (2000 mm High Cabinet in Dual-Row
Aisle Containment)
Figure 4-176 Routing cables for the network cabling cabinet
(1) Power cable
4.12.4 Installation Positions for Monitoring Components
Figure 4-177
Issue Draft A (2015-06-29)
shows the installation positions of monitoring components.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Hardware Installation
(2) Signal cable