IDS2000 Intelligent Micro-Modular Data Center
Installation Guide (2000 mm High Cabinet in Dual-Row
Aisle Containment)
Figure 4-7 PDU8000 base (unit: mm)
Procedure
Step 1 Unscrew the four M6 screws and remove the adjustable feet from the base, as shown in
4-8.
Figure 4-8 Removing adjustable feet
Step 2 Move the adjustable feet forward to leave a distance of 100 mm, as shown in
Step 3 Secure the adjustable feet to the base using the four M6 screws.
Step 4 Deploy the PDU8000 base at the planned installation position.
----End