How to Install Front Handles/Rack Mounting Flanges

How to Install the Rack-mount Kit (Option 1CM)

The rack-mount kit includes two flanges (locking side plates) for mounting the E4991A on
a rack (482.6 mm/19 inches) conforming to the EIA Standard. While referring to Figure
2-8, install the rack-mount kit by following these steps.
Step 1. Remove the adhesive-backed trim strip (1) from each side of the outer frame of the
E4991A front panel.
Step 2. Use the provided screws to mount a rack-mounting flange (4) on each side of the E4991A
front panel frame.
Step 3. Remove the four bottom feet of the E4991A (lift the bar marked TAB on the inner side of
the foot and slide the foot toward the bar).
Step 4. Mount the E4991A on the rack.

How to Install the Rack-mount and Handle Kit (Option 1CP)

The rack-mount and handle kit includes both the rack-mounting flanges (locking side
plates) and front handles. While referring to Figure 2-8, install the rack-mount kit by
following these steps.
Step 1. Remove the adhesive-backed trim strip (1) from each side of the outer frame of the
E4991A front panel.
Step 2. Use the provided screws to mount a front handle (2) and rack-mounting flange (4) on each
side of the E4991A front panel frame.
Step 3. Remove the four bottom feet of the E4991A (lift the bar marked TAB on the inner side of
the foot and slide the foot toward the bar).
Step 4. Mount the E4991A on the rack.
24