6.
Start-up
But because of the complex application possibilities we must restrict ourselves to explaining the start-up of
standard applications.
6.1 Preparatory measures
6.1.1 After unpacking the goods
After unpacking the goods and checking them for complete delivery following measures are to be carried out:
Visual control for transport damage
Should any external damages to the KEB COMBIVERT be visible get in tough with your forwarding agent
and return the unit with a corresponding report to KEB.
Check the voltage class:
Absolute check before assembly whether the supply voltage of the KEB COMBIVERT matches the applica-
tion.
6.1.2 Installation and connection
The EMC-conform installation of the inverter is described in the Instruction Manual Part 1. Installation and con-
nection instructions are found in the instruction manual part 2.
The mounting surface of the inverter must be bright.
If necessary, use contact lacquer as protection against corrosion.
Connect the earthing strip to central point in the control cabinet
Picture 6.1.3 Installation and connection
© KEB, 2012-10
COMBIVERT F5-A, -E, -H
Preparatory Measures
6
Page 6.1 - 3