WIRING AC POWER

DANGER
Turn off AC power at the source (circuit breaker
panel) before accessing the wires in the
SwingSmart DC junction box. Follow facility
Lock Out/Tag Out procedures. Make sure both
the DC and AC power switches, on the side of
the SwingSmart DC control box are in the off
position.
Place power switches
in OFF position.
DO NOT connect the
WARNING
115VAC service outlet to 208 or
230VAC power supply wires! To
use the 115VAC service outlet on
a 208 or 230VAC installation, the
electrician needs to run an extra
neutral wire to the operator from
the power source and wire the
service outlet per code.
Service outlet
Junction box
cover and label
40
| www.hysecurity.com
Figure 18. Wiring AC Power
SWINGSMART DC PROGRAMMING AND OPERATIONS MANUAL
CAUTION
Wiring of gate operators must conform to the
NEC standards and comply with all local codes.
If you plan to connect to 208/230VAC power,
read the WARNING in the illustration below.
The voltage selector switch on the AC Power
board must be moved to the 230V position or
damage to the operator will occur and void
the Limited Warranty.
Voltage selector
switch is factory
set to 115V.
If power input is 208/230V,
move the switch so 230V
appears and change the
label on the junction
box cover.
POWER
High voltage
protection cover
MX3640-01 REV. D ©2018