PAD CONDITION

Pouring the Concrete

1. Follow the local building codes to identify the
frost line and determine the required depth
of the concrete pad. HySecurity recommends
a minimum 16-inch (40.6cm) depth with a
minimum 2-inch (51cm) extension above
ground level. Refer to Figure 3.
2. Before pouring the pad, consider conduit
placement so it fits within the confines of the
cutout in the SwingSmart base plate as shown
in Figure 3. Run separate conduits for:
z high voltage swiring (115/230V supply power)
including equipment ground
z low voltage wiring (12V and 24V accessory
power) including:
• vehicle loop control wiring
• primary/secondary connections
z earth ground (NEC/NFPA)
NOTICE
SwingSmart provides a 6 x 7-inch (15.2 x
17.7cm) cutout in its chassis base for conduit.
Refer to Figure 3. The design also provides a
9.6-inch (24.4cm) height between the control
box and chassis base for pulling and placement
of wires.
3. Extend conduit height 2-inches (51mm) above
the pad (4-inches/102mm above ground level).
Make sure the concrete forms are square with
the gate and the pad is level. Refer to Figure
3 for minimum pad dimensions.
CAUTION
Be sure to restrict conduit to the 6 x 7-inch
(15.2 x 17.7cm) cutout in the chassis base if
you plan to use the extended battery backup
kit. The area designed for the optional dual
50Ah batteries may be obstructed if conduit
is routed elsewhere.
26
| www.hysecurity.com
SWINGSMART DC PROGRAMMING AND OPERATIONS MANUAL
30.2"
76.7cm
26.8"
(68cm)
9.6" (24cm)
control box
height
Earth ground
Ground level
High voltage
10.5"
(26.7 cm)
(13.4 cm)
10.5" (26.7 cm)
5.7" (14.5 cm)
23" (58.4 cm)
minimum
20" COVER
(50.8 cm)
2.5"
2.8"
(6.3 cm)
(7.1 cm)
7.6" (19.3 cm)
1.8" (4.6cm)
6" x 7"
(15.2cm x 17.7cm)
Cover Area
Chassis Base
14.5 x 16"
Conduit Area
36.8 x 40.6cm
Figure 3. Pad Condition and Dimensions
INSTALLATION
Stub out conduit
4-inches (102mm)
above ground
level
2-inch (51cm)
height above pad.
Vehicle Loop
control wires
Primary/Secondary
wires - optional
Low voltage/
Communication
wires
21" (53.3 cm)
minimum
5.3"
Output Shaft Center
Drill 4 holes for
½" x 3 ½" concrete
anchors
14"
(35.6 cm)
6" x 7" conduit
12" (30.5 cm)
area
minimum
2" minimum
(51mm)
Pad Depth: 16" minimum
Output
Shaft
Center
22" COVER
(56 cm)
1.5"
(3.8 cm)
3.5"
(8.9 cm)
MX3640-01 REV. D ©2018
(41cm)

Advertisement

Table of Contents
loading

This manual is also suitable for:

Swingsmart dcs20Swingsmart dc20

Table of Contents