In the default setting, the check box is not enabled.
Note
The batch types will be generated from all projects in the multiproject.
Transfer messages
Select the check box if you want the BATCH messages transferred to the PCS 7 OS prior to
the action "Merge/Compile". In the default setting, the check box is not enabled.
Batch process cells in the projects
This area of the dialog displays the batch process cells in the projects of a multiproject in the
form of a table. One project of the multiproject is listed per row. Information about the project
is shown in the relevant columns.
Project
In the "Project" column, you will see the name of the project.
Note
Projects that have been removed for editing are indicated by a transparent icon. Such projects
cannot be compiled because the check box is grayed out.
Path
In the "Path" column, you will see the path of the project.
Batch process cell
The "Batch process cell" column displays the name of the batch process cell that you assigned
in the BatchCC.
Note
In projects that are removed for editing you can supplement the batch types of all batch process
cells with operation, phase, and process tag types. These batch process cells are indicated
by a special marking, a blue bar.
SIMATIC BATCH V8.2
Operating Manual, 02/2016, A5E35958174-AA
Context help references
14.1 Dialogs
1045