Installing a Rack

007-4566-001
Warning:
Employ a minimum of two people to lift the system module or
modules off the shipping pallet, to move the module(s) from one location to
another, and to install the module(s) in a rack. Otherwise, someone could be
seriously injured.
Do not move the system while it is connected to power.
Danger:
Keep fingers and conductive tools away from high-voltage areas. Failure to
follow these precautions will result in serious injury or death. The high-voltage areas
of the system are indicated with high-voltage warning labels.
Ensure that a qualified electrician has properly installed the power receptacles.
Set all circuit breakers to the OFF (
cord.
Warning:
Use the following guidelines to prevent the rack from toppling over.
Otherwise, people could be seriously injured and/or equipment could be damaged.
Follow these guidelines to prevent the rack from toppling over:
Make sure that only one module is extended out of the rack at one time.
Install all equipment in the lowest available position in the rack.
Ensure that the tip tray is bolted to the front of the rack.
This section describes how to install a rack at your site location, as follows:
"Preinstallation Activities" on page 6
"Unloading and Moving System Equipment" on page 10
"Removing a Short Rack from the Shipping Crate" on page 13
"Removing a Tall Rack from the Shipping Crate" on page 16
"Positioning and Leveling a Single-rack System" on page 19
) position before you plug in the system power
O
Installing a Rack
5

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Origin 350 and is the answer not in the manual?

Questions and answers

Table of Contents