5.3. Unpacking Power Cabinet

5.3.1. Before unpacking

Unloading Power Cabinet
The delivery truck only unloads the pallet carrying the Power Cabinet.
The delivery truck will not move the Power Cabinet to its final location.
The placement of the Power Cabinet to its final location is the
responsibility of the Contractor. Upon request it is possible to order a
truck with a crane.
Do not pollute the environment with plastic and cardboard packing.
Dispose of the package elements according the regional applicable
regulations regarding the environment.
Prerequisites:
All construction work is completed.
The product is delivered by a transport company at the confirmed date of delivery.
Make sure that the Power Cabinet has not been shaken or tilted over 30⁰.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
CAUTION
Meaning of SchockWatch's indicator
HVC-R 100/150 V2 E-Bus Charger Installation Guide
NOTICE
Page 56 of 133