Placing the Power Cabinet on metal frame foundation
A
Foundation
B
Power Cabinet
C
Cables
D
Tapped holes
1.
Carefully lower the Power Cabinet (B) onto the foundation (A).
2.
Make sure that you do not trap the cables (C).
3.
Make sure that the cabinet is aligned with the tapped holes (D).
Connecting the Power Cabinet with its foundation
4.
Insert the M16 bolts (A) fitted with the washers into the holes in the corners (4x).
A minimum of three M16 bolts are need to applied to securely mount the
Power Cabinet onto the foundation.
In case of placing two Power Cabinets next to each other and (100 mm
distance) against the wall, then one Power Cabinet can be secured by
three M16 bolts on to the foundation.