4. Construction

4.1. About construction

The construction phase includes all works required to prepare the location and make it ready
for the placement and connection of the HVC-R 100/150 V2 E-Bus Charger. The construction
phase can start when:
All engineering work is done.
All permits are granted.
The grid connection is available.
The planning steps for the construction phase are shown in the figure below:
Indication of Construction phase on the planning diagram
B1
Civil engineering works
Construction of the foundation - see section Providing foundation for the Power
Cabinet on Page 39 and section Mounting of the Dual Depot Charge Box on Page 44.
Installation of the cable connections - see section Cable routing on Page 47.
Construction of the bus stop surrounding - see section Geometry of infrastructure on
Page 28.
B2
Electrical engineering works
See section Electrical installation on Page 33 and section Adapting the grid on Page
26.
B3
Internet access (optional)
This step can be ignored if the location has sufficient 3G coverage. Otherwise, an
Ethernet (RJ45) connection has to be installed - see section Internet connection on
Page 53.
B4
Transport
Arrangement for the delivery of the HVC-R 100/150 V2 E-Bus Charger with the ABB
Delivery department - see Contact information on Page 12 for contact details. The
delivery time is at least four months.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
HVC-R 100/150 V2 E-Bus Charger Installation Guide
Page 38 of 133