4.2. Providing foundation for the Power Cabinet

4.2.1. Available options

Use the appropriate foundation for the type of surface that the Power Cabinet will be installed
on:
Soil
Use a concrete foundation to get a firm fixation on soil.
A concrete foundation can be ordered separately. See section Accessories on Page
18. For detail drawings see Appendix C Dimensions of the Power Cabinet's Concrete
Foundation.
Solid floor
1. Use a metal frame foundation to guide the cables from the cabinet to the cable
duct. This foundation can be ordered separately. See section Accessories on Page
18. For detail drawings see Appendix D Dimensions of the Power Cabinet's Metal
Foundation.
2. The Power Cabinet is installed directly on a solid floor, through which the floor is
accessible from below (related to the feed through of the cables). For detail
drawings see Appendix A Dimensions of the Power Cabinet.
The cables must be embedded in the ground within cable conduits. See section Cable routing
on Page 47 and section Civil installation on Page 35.
It is advised to install traction wires into the conduits to install the
electrical cabling afterwards.
Be aware of the bending radius of the AC power input cables when using
the metal frame foundation. This metal frame foundation has a height of
180 mm.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
HVC-R 100/150 V2 E-Bus Charger Installation Guide
NOTICE
NOTICE
Page 39 of 133

Advertisement

Table of Contents
loading

Table of Contents