Customer Acceptance Form (Caf) - ABB HVC-R 100/150 V2 Installation Manual

E-bus charger
Table of Contents

Advertisement

6.2. Customer Acceptance Form (CAF)

After the commissioning is completed, the Owner / Site Operator will sign the Customer
Acceptance Form (CAF). In certain circumstances ABB will be represented by a project
engineer.
The CAF contains information about:
the project (number, location, charger type);
a checklist regarding the delivery;
the commissioning SAT checklist;
A list of remaining items.
Once the CAF is signed, the customer support will be handled by the ABB Service department.
If there are any remaining items, they can be listed on the CAF document, together with the
agreed solution and the expected date of completion.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
HVC-R 100/150 V2 E-Bus Charger Installation Guide
Page 116 of 133

Advertisement

Table of Contents
loading

Table of Contents