Lightning Protection - ABB HVC-R 100/150 V2 Installation Manual

E-bus charger
Table of Contents

Advertisement

HVC-R 100/150 V2 E-Bus Charger Installation Guide
3.10.

Lightning protection

One electrode (ground rod) of maximum 10 Ω must be placed in to the earth near the
foundation of the Power Cabinet. In some cases, additional grounding is required at the Dual
Depot Charge Box's side. This depends on the local regulations and should be determined by
the Contractor.
If the grid is TT based, consult the grid Owner. It is possible that an extra 0,9 Ω electrode will
be required. This requirement must be determined by the Contractor.
Consult a local specialist for the options of lightning protection. The charge system has to be
within the protection angle of the lightning distraction. This requirement must be determined
by the Owner and a local specialist (according to NEN-EN-IEC 62305).
The implementation of the lightning protection depends on the local laws, safety and electrical
regulations. This requirement must be determined by the Contractor and Owner of the site /
HVC-R 100/150 V2 E-Bus Charger.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
Page 37 of 133