3. Preparation

3.1. Project planning

Careful project planning is necessary before an HVC-R 100/150 E-Bus Charger is purchased
and put into operation. The different phases of the full project plan are shown in the figure
below:
A. Preparation
The Owner / Site Operator has ordered an HVC-R 100/150 V2 E-Bus Charger. In this
phase all preparation work must be completed before the Contractor can perform the
civil and electrical works. See About preparation on Page 23.
B. Construction
The Contractor performs all civil and electrical works. See About construction on Page
38.
C. Placement and Connection
The location is mechanically and electrically ready to receive the HVC-R 100/150 V2
E-Bus Charger. See About placement and connection on Page 54.
D. Commissioning
The delivery department will bring the HVC-R 100/150 V2 E-Bus Charger into
operation. See Commissioning preparation on Page 115.
E. Service and Maintenance
The HVC-R 100/150 V2 E-Bus Charger is operational. There are various options for
service and maintenance. See About Service and Maintenance on Page 117.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
Diagram of the project's phases