6. IMPORTANT: Place the foundation (A) in the correct position. Mind the desired
location of the Dual Depot Charge Box's door.
7. Make sure that the front top surface of the foundation is at least 15 mm above ground
level (see figure above).
8. Make sure that the top surface of the foundation is leveled.
9. Route the conduits through the foundation's holes (B).
10. Fill the space surrounding the foundation in the ground and the channels for the
conduits with filling material (e.g. sand). Filling material should be packed 2 – 3 times
with a packing machine until the desired ground level is obtained. Avoid having filling
material enter the foundation's interior.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
HVC-R 100/150 V2 E-Bus Charger Installation Guide
Page 45 of 133