5.2. Routing the cables

1.
Unpack the cables. See Cable routing on Page 47 for details on which cables are needed.
2.
Remove the top cover plate (B) and the front cover plate (C) from the foundation (A) by
loosening the bolts (D).
3.
Put the front cover plate (C) and its bolts (D) in a safe location as it will be installed again
later on.
Step 2 and 3 are only applicable when the Power Cabinet is placed on a
concrete foundation.
The top cover plate is not needed any more after the cabinet is placed on
the foundation.
5.
Route the DC power cables through the cable conduit.
6.
Route the AC auxiliary power, PE wire, Interlock cable and Ethernet cable (if required)
through the other cable conduit.
7.
Route the communication Ethernet cable through the extra 40 mm cable conduit.
8.
For the DC power cables, make sure that a cable length of 1000 mm and 1500 mm is
available above the surface for internal routing respectively in the Power Cabinet and in
the Dual Depot Charge Box.
9.
For the other cables, make sure that a cable length of 3000 mm is available above the
surface for internal routing in the Power Cabinet and the Dual Depot Charge Box.
This extra cable length is required to connect the cables with the
connectors in the Power Cabinet and the Dual Depot Charge Box without
any problems.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
Removing the foundation's cover plates
HVC-R 100/150 V2 E-Bus Charger Installation Guide