5.5. Installing the Power Cabinet onto a foundation

5.5.1. Connecting Power Cabinet to a foundation

Prerequisites:
Tools: spanner (size 24).
Cover caps (4x) that were removed from the Power Cabinet (bag with parts).
The Power Cabinet is about 500 mm above its location.
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
Make sure that personnel cannot be crushed or become trapped while
moving the Power Cabinet.
Placing the Power Cabinet on concrete foundation
A
Foundation
B
Power Cabinet
C
Cables
D
Tapped holes
Document: v0.1 / Document No.: TBA | Date: XX-08-2021