5.5.3. Loosening the sliding plate of the guidance plates

Prerequisites:
Tools: spanner (size 13).
1.
Loosen the bolts (A).
2.
Move the sliding plate (B) of the 2 guidance plates.

5.5.4. Routing cables through the guidance plates

The method of routing cables through the Power Cabinet's floor
1.
Route the cables (A) through the right guidance plates (B).
2.
Make sure that there is sufficient cable length to reach the connectors at the top of the
cabinet.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021