3.2. About preparation

The planning steps for the preparation phase are shown in the figure below:
A1
Ordering
Order the HVC-R 100/150 V2 E-Bus Charger.
A2
Engineering
The Owner / Site Operator selects a Contractor to perform the civil and electrical
installation works. The Contractor is responsible for all construction documentation of
the site, i.a.: drawings, calculations, certifications, licenses and test reports.
The location of the HVC-R 100/150 V2 E-Bus Charger must be selected. See section
Location on Page 27 and section Geometry of infrastructure on Page 28.
A3
Get permits
Make sure that all the permits required by local regulations had been acquired.
See section Required permits on Page 24.
A4
Upgrade grid
If required, upgrade the electrical grid connection to 3-phase 400 V AC. See section
Adapting the grid on Page 26.
A5
Transport foundation(s) on request
If it is necessary to order the foundation(s), transport of the foundation(s) must be
arranged with the ABB Delivery department. See Contact information on Page 12 for
contact.
Document: v0.1 / Document No.: TBA | Date: XX-08-2021
Diagram of preparation phase's steps
HVC-R 100/150 V2 E-Bus Charger Installation Guide
Page 23 of 133

Advertisement

Table of Contents
loading

Table of Contents