RT9150E OPERATOR MANUAL
17,690 kg (39,000 lb) Cast Counterweight
Installation
Read and understand the following when removing and
installing the counterweight or counterweight stand, to
avoid serious injury or death.
•
Outriggers must be fully extended and set and crane
level before installation or removal of counterweight.
•
Lifting operations are not permitted with any
counterweight on the carrier deck except for the
removal or installation of the counterweight.
•
Boom is not permitted over carrier deck when the
boom angle is less than 30° and any counterweight is
positioned on deck.
•
Hookblock is not permitted to come in contact with
counterweight during removal or installation.
•
Travel is not permitted with any counterweight on
carrier deck.
•
Counterweight assembly must be completed on the
ground not on the carrier counterweight stands.
8162-2
17,690 kg (39,000 lb) Cast Counterweight
Grove
DANGER
Published 2-23-2017, Control # 644-00
SET-UP AND INSTALLATION
1.
Rig the crane with three parts of line.
2.
The 17,690 kg (39,000 lb) cast counterweight assembly
may
be
lifted
in
one
configurations.
Boom Configuration
0-0-0-0-0
0-0-0-0-50
(30 ft radius)
3.
Enter RCL code 1100. Refer to RCL Main Menu, page 3-
75.
4.
Connect sling assemblies to the cast counterweight
using the installation lifting holes (Figure 4-15).
5.
Lift and place the counterweight onto the support
bracket (Figure 4-15) on the ground.
6.
Lift and place the counterweight/support bracket
assembly onto carrier counterweight stands using the
support bracket lifting eyes (Figure 4-16).
Lifting Eyes
8162-4
Support Bracket
of
the
following
boom
0-0-0-50-0
FIGURE 4-15
4-15
4