Commissioning

8
Commissioning
This section shows a step-by-step procedure for starting up exemplarily a WAGO
fieldbus node.
Good example!
This description is just an example and only serves to describe the procedure for
a local start-up of a single fieldbus node with a PC under Windows.
In principle, only a few steps are required for start-up.
To enable communication from your PC to the fieldbus coupler/controller over
network, both must be in the same network. This requires that you first determine
the IP address of the PC and then assign a corresponding IP address to the
fieldbus node. There are several options being available for IP address
assignment.
The description of these single work steps can be found in the corresponding
following chapters.
Connecting PC and fieldbus node
Determing IP address of the PC
Assigning IP address to the fieldbus node
Applying IP address permanently (option "static")
Following the commissioning descriptions after which the fieldbus node is ready
for communication, the following topics are described:
Preparing the Flash File System
Synchronizing the System Time
Restoring Factory Settings