Creating a Task Configuration

With task configuration, you set the time response and priority of individual
program function blocks.
Watchdog
In an application program without task configuration, there is no watchdog that
monitors the cycle time of the application program (PLC_PRG).
Create a task configuration in the following manner:
1.
To open task configuration, double click on "Task configuration" in the
"Resources" column.
Figure : Task configuration
2.
To create a task configuration, right click on "Task configuration" and select
"Append Task" in the context menu.