Lifting

When lifting the instrument, use procedure appropriate to lifting a heavy
object, such as, bending at the knees while keeping your back straight and
upright. Grasp the instrument at the bottom in the front and at the rear of
the unit. Although one person can lift the unit, it is desirable to have two
persons lifting, one by grasping the bottom in the front and the other by
grasping the bottom in the rear.
Equipment Damage Do not attempt to lift the instrument by the cover or
other external fittings.
The Model 42i Trace Level is shipped complete in two containers. If there
is obvious damage to the shipping containers when you receive the
instrument, notify the carrier immediately and hold for inspection. The
carrier is responsible for any damage incurred during shipment.
Use the following procedure to unpack and inspect the instrument.
1. Remove the instrument from its shipping container and set it on a table
or bench that allows easy access to both the front and rear.
2. Remove the cover to expose the internal components.
3. Remove the packing material
2-1
Inspection" on page
Procedure" on page
2-2
Devices" on page
2-9
(Figure
2-1
2-5
2–1).
Model 42i Trace Level Instruction Manual