Throttle Body Removal And Installation; Throttle Body Disassembly And Assembly - Suzuki AN400 Service Manual

Hide thumbs Also See for AN400:
Table of Contents

Advertisement

Throttle Body Removal and Installation

Removal
1) Remove the air cleaner box. Refer to "Air Cleaner
Box Removal and Installation (Page1D-9)".
2) Remove the throttle cables (1).
3) Remove the fuel hose (2).
4) Remove the throttle body assembly (3).
5) Remove the intake pipe (4).
1
Installation
Install the throttle body assembly is in the reverse order
of removal. Pay attention to the following points:
• Install the intake pipe. Refer to "Cylinder Disassembly
and Assembly (Page1D-33)".
• When installing the throttle body to the intake pipe, fit
the projection on the throttle body to the depression of
the intake pipe.
• Connect the throttle cables properly. Refer to "Throttle
Cable Removal and Installation (Page1D-10)".
• Adjust the throttle cable play. Refer to "Throttle Cable
Play Inspection and Adjustment in Section 0B
(Page0B-11)".
B705H11406070
2
3
4
I705H1140205-01
I705H1140206-01

Throttle Body Disassembly and Assembly

Disassembly
1) Remove the throttle body. Refer to "Throttle Body
Removal and Installation (Page1D-13)".
2) Remove the insulator (1) and fuel injector (2).
1
3) Remove the intake pipe (3) and O-ring (4).
3
4) Remove the IAP sensor (5) and O-ring (6).
5
5) Remove the ISC valve (7).
Engine Mechanical:
1D-13
B705H11406073
2
I705H1140208-01
4
I705H1140209-02
6
I705H1140210-01
7
I705H1140211-01

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AN400 and is the answer not in the manual?

Table of Contents

Save PDF