13.7.
13.7. Battery Open Alarm for Forced
Battery Open Alarm for Forced
Load Sharing
Load Sharing
The recommended practice for Forced Load Sharing which employs periodic Open Battery
Testing is to only enable the test on the Primary ATevo. During load sharing, the Primary ATevo
will dictate the battery open test voltage setting to all Secondary chargers when a scheduled
test runs. It is always possible to manually start a Battery Open Test from a Primary or
Secondary when load sharing is active.