8.3.3 Test Screens
8.3.3 Test Screens
The remaining screens are test screens. They prompt the user through an interactive process
to verify ATevo's operation. The process will:
• Require the user to confirm that LED indicators are lit, that relays change state, and that
the set points are correct.
• Simulate alarm conditions and prompt the user to verify the alarms operate and are
confirmed by any connected SCADA devices.
• Explain how to verify ATevo calibration and automatically enter calibration mode if
required.
After the Hindle Health System completes testing, ATevo will return to the Home Screen. An
event will be added to the log file along with a time and date stamp. The results of each test
are included in the log file. The result status will indicate that each test PASSED, FAILED, or was
NOT RUN. The resulting log file can be used to prove NERC compliance requirements for things
such as verifying correct float voltage.
Copyright HindlePower Inc. 2021
ATevo O&SI - 1PH Input Group I (6-25 Adc) - 1.1_en
Last modified: 27 July 2023
Page 189 of 316

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ja5011-51

Table of Contents