5.5. Install Power Cabinet onto the foundation

5.5.1. Connect Power Cabinet to foundation

Preconditions:
Tools: spanner (size 24).
Cover caps (4x) that were removed from the Power Cabinet (bag with parts).
The Power Cabinet is about 19.69 Inch above its location.
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system.
Make sure that personnel cannot be crushed or become trapped while
moving the Power Cabinet.
Placement on concrete foundation
A
Foundation
B
Power Cabinet
C
Cables
D
Tapped holes
Revision: 1.2