Make Sure That The Floor Space For The Evse And The Airflow Around The Evse Is Correct; Prepare The Foundation; Prepare The Foundation - General Procedure; Prepare A Prefab Concrete Foundation For The Power Cabinet - ABB Terra HP Generation 4 CE Ionity Installation Manual

Table of Contents

Advertisement

Pre-installation
7. Make sure that the site complies with the relevant usability standards, such as
ADA and DIN 18040:
a. Limit the curb heights.
b. Take into account the limited reach of a wheelchair user.
For usability standards specifications, refer to section 12.14.3.
8. Make the site as safe as possible.
a. Make sure that the EVSE can be clearly seen and monitored.
b. Apply 24/7 security control.
c. Install sufficient lighting.
4.3
Make sure that the floor space for the EVSE and the
airflow around the EVSE is correct
1. Make sure that the floor spaces meet the requirements. Refer to section 12.15.
2. Make sure that the air flow inlet and outlet cannot get blocked. Think of snow or
objects.
4.4

Prepare the foundation

4.4.1

Prepare the foundation - general procedure

1. Select the correct foundations, based on the underground.
2. Prepare the foundation for the power cabinets.
3. Prepare the foundation for the charge posts.
4. If you use a concrete foundation, install the grommet plate. Refer to section 4.5.
5. Install the cable support. Refer to section 4.6.
4.4.2

Prepare a prefab concrete foundation for the power cabinet

Preliminary requirements
30
Caution: Make sure that the foundation of the charge post is level. You
cannot use shims to level the charge post.
Type
Prefab concrete foundation
Metal foundation
Type
Prefab concrete foundation
Metal foundation
Custom foundation
Prefab concrete foundation. Refer to section 12.16.1.
Procedure
Refer to section 4.4.2.
Refer to section 4.4.3.
Procedure
Refer to section 4.4.4.
Refer to section 4.4.5.
Refer to section 4.4.6.
6AGA000032-0115-EN | 004