B4
Transport
Arrangement for the delivery of the HVC-PD E-Bus Charger with the ABB Delivery
department. See Contact information on Page 14 for contact details. The delivery time
is at least four months.

4.2. Construct foundation of the Power Cabinet

4.2.1. Options

Use the correct foundation for the type of surface that the Power Cabinet will be installed on:
Soil
Use a concrete foundation to get a firm fixation on soil.
Concrete foundation cannot be ordered separately. It must be manufactured by
customer
. For detail drawings of the pre-fabricated concrete foundation see Appendix
E Dimensions concrete foundation Power Cabinet.
Solid floor
1. Use a metal frame foundation to guide the cables from the cabinet to the cable
duct. This foundation can be ordered separately. See section Foundation for
Power Cabinet on Page 20. For detail drawings see Appendix E Dimensions
metal frame foundation Power Cabinet.
2. The Power Cabinet is installed directly on a solid floor, through which the floor
is accessible from below (related to the feed through of the cables). For detail
drawings see Appendix A Dimensions Power Cabinet.
The cables must be embedded in the ground with a cable conduit. See section Cabling on
Page 49 and section Civil installation on Page 36.
It is advised to install traction wires into the conduits to install the
electrical cabling afterwards.
Be aware of the bending radius of the AC power input cables when using
the metal frame foundation. This metal frame foundation has a height of
7.09 Inch.
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022
HVC‐PD E‐Bus Charger Installation Guide 
NOTICE
NOTICE
the
Page 39 of 146

Advertisement

Table of Contents
loading

Table of Contents