Commissioning; Commissioning Guidelines - Siemens SINAMICS G115D Operating Instructions Manual

Distributed drive for conveyor applications
Hide thumbs Also See for SINAMICS G115D:
Table of Contents

Advertisement

Commissioning

6.1

Commissioning guidelines

Overview
SINAMICS G115D Wall Mounted distributed drive
Operating Instructions, 07/2023, FW V4.7 SP14, A5E52808211A AA
1. Define the requirements to be met by the drive
for your application.
Preparing for commissioning (Page 107)
2. Restore the factory settings of the converter if
necessary.
Restoring the factory settings (Page 125)
3. Check if the factory setting of the converter is
sufficient for your application.
Factory settings (Page 107)
4. Perform quick commissioning of the drive in
one of the following ways:
AUTOHOTSPOT
Quick commissioning with a PC (Start‐
drive) (Page 116)
Quick commissioning with the SINAM‐
ICS G120 Smart Access (Page 123)
5. Check if additional converter functions are re‐
quired for the application.
Advanced commissioning (Page 129)
6. If necessary, adapt the drive.
Advanced commissioning (Page 129)
7. Save your settings and perform data backup.
Saving the settings in the converter
(RAM → EEPROM) (Page 124)
Data backup and series commissioning
(Page 351)
6
105

Advertisement

Table of Contents
loading

Table of Contents