Commissioning

5.1

Commissioning guidelines

Overview
SINAMICS G115D distributed drive
Operating Instructions, 09/2020, FW V4.7 SP13, A5E48681219B
1. Define the requirements to be met by the
drive for your application.
Preparing for commissioning
(Page 84)
2. Restore the factory settings of the
converter if necessary.
Restoring the factory settings
(Page 98)
3. Check if the factory setting of the
converter is sufficient for your application.
Factory settings (Page 84)
4. Perform quick commissioning of the drive
in one of the following ways:
Quick commissioning with DIP
switches (Page 89)
Quick commissioning with a PC
(Startdrive) (Page 91)
5. Check if additional converter functions are
required for the application.
Advanced commissioning
(Page 101)
6. If necessary, adapt the drive.
Advanced commissioning
(Page 101)
7. Save your settings and perform data
backup.
Saving the settings in the
converter (RAM → EEPROM) (Page 97)
Data backup and series
commissioning (Page 281)