Chapter 3: FRU Removal and Replacement Procedures
Replacing Node Power Supplies
Replacing Node Power Supplies
Obtaining a
Replacement Node
Power Supply
94
• The rebuild process takes approximately 3 hours (normal system
load).
• You can continue to use the DXi6900 G1 normally while the
drive rebuilds. System performance may be reduced during the
rebuilding process.
4 If necessary, replace the front bezel on the Node.
5 In the remote management console, delete any administrative alerts
and close any service tickets.
This section describes how to remove and replace power supplies in the
DXi6900 G1 Node and contains the following sections:
•
Obtaining a Replacement Node Power Supply
•
Replacing a Node Power Supply
Note: DXi6900 G1 uses redundant, hot-swappable power supplies.
You do not need to shut down the system to remove and
replace a power supply.
Caution: The Node requires one power supply for normal operation.
Remove and replace only one power supply at a time if the
system is powered on.
Before beginning the replacement procedure, make sure that you have
the required replacement kit. The appropriate replacement power
supply will be provided by Quantum Customer Support (see
You will need the following items to perform this procedure:
• Replacement power supply kit provided by Quantum Customer
Support.
• ESD grounding wrist strap (included in the replacement kit)
Figure
Quantum DXi6900 G1 User's Guide
49).