Figure 43 Installing the
DXi6900 G1 Node in the Rack
Slide-release lock button
Quantum DXi6900 G1 User's Guide
8 Locate the rear rail standoff on each side of the system and lower
them into the rear J-slots on the slide assemblies.
9 Rotate the Node downward until all the rail standoffs are seated in
the J-slots.
10 Push the Node inward until the lock levers click into place.
11 Press the slide-release lock buttons on both rails and slide the Node
into the rack.
12 Reconnect all power, SAS, Ethernet, and Fibre Channel cables on the
rear of the Node (see
13 Turn on the system
page 23).
Chapter 3: FRU Removal and Replacement Procedures
Inner slide rails
Lock lever
Appendix A, Cabling
(Turning On and Shutting Down the System
Opening and Closing the Node
Rear rail standoffs
Rear rail J-slots
Diagrams).
on
85

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dxi6900 g1Dxi6900 g2

Table of Contents