5.5.3

Go online and start quick commissioning

Procedure with STARTER
Proceed as follows to start the quick commissioning of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with
which you wish to go online.
3. Download the hardware configuration found online in
your project (PG or PC).
Significance of the symbol in front of the inverter:
(A) The inverter is online.
(B) The inverter is offline
4. When you are online, double-click on "Control Unit".
5. Start the commissioning wizard:
You have started the quick commissioning of the inverter.
Procedure with Startdrive
Proceed as follows to start the quick commissioning of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with which you wish to go online.
3. Once you are online, select "Commissioning" → "Commissioning Wizard":
You have started the quick commissioning of the inverter.
Converter with the CU240B-2 and CU240E-2 Control Units
Operating Instructions, 01/2017, FW V4.7 SP6, A5E34259001B AD
5.5 Quick commissioning with a PC
.
Commissioning
153