Commissioning
5.5 Basic commissioning with STARTER
You have set the USB interface.
STARTER now shows the inverters connected via USB.
5.5.3

Go online and start wizard for basic commissioning

Procedure
Proceed as follows to start the basic commissioning online with the converter:
1. Select your project and go online:
2. Select the device or the devices with which you wish to go
online.
3. Download the hardware configuration found online in your
project (PG or PC). STARTER shows you which converter
it is accessing online and which offline:
4. When you are online, double-click on "Control Unit".
5. Start the wizard for basic commissioning.
You are online and have started basic commissioning.
70
The converter is online
The converter is offline
.
Converter with control units CU240D-2
Operating Instructions, 04/2014, FW V4.7, A5E34262100B AA

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cu240d-2

Table of Contents