Commissioning

4.2 Commissioning with BOP-2 operator panel

4.2
Commissioning with BOP-2 operator panel
4.2.1

Start quick commissioning and select the application class

Starting quick commissioning
Preconditions
● The power supply is switched on.
● The operator panel displays setpoints and actual values.
Procedure
Proceed as follows to carry out quick commissioning:
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
To start quick commissioning, in the "SETUP" menu, press the OK key.
If you wish to restore all of the parameters to the factory setting before the quick
commissioning, proceed as follows:
1. Press the OK key.
2. Switchover the display using an arrow key: nO → YES
3. Press the OK key.
You must select the application class if you are not using a PM230, but instead, a PM240-2,
PM240P-2 or PM330 Power Module. The next steps after having selected an application
class are described in the operating instructions.
Select the motor standard.
● KW 50HZ: IEC
● HP 60HZ: NEMA
● KW 60HZ: IEC 60 Hz
Set the inverter supply voltage.
Select the motor type. If a 5-digit motor code is stamped on the motor rating plate, select the
corresponding motor type with motor code.
Motors without motor code stamped on the rating plate:
● INDUCT: Third-party induction motor
● 1L... IND: 1LE1, 1LG6, 1LA7, 1LA9 induction motors