Chapter 4
Deploying the C65/76M
Deployment and Commissioning Process
Figure 4-15 Network Element Dialog Box
Click the Commission button from the Configuration tab to start the subchassis discovery, which
allows the C65/76M to determine which modules are installed on the switch or router, and also allows
CEMF to start monitoring the switch or router.
Note
Commissioning may take a few minutes.
Unlike the Auto Discovery process (see the
"IP Auto Discovery" section on page
4-5), no additional
parameters need to be specified. These parameters were specified in the manual Deployment Wizard
(Figure
4-11). After the object is commissioned, the Physical view will resemble
Figure
4-16.
Cisco 6500/7600 Series Manager User Guide
4-19