6.11.4 mHMI APPLICATION - BLUETOOTH DEVICE PAIRING
See chapter "BLUETOOTH MODULE AND mHMI APPLICATION".
7
INITIAL START-UP
7.1 PREPARATION FOR THE FIRST START-UP
!
!
Before proceeding with the activities leading to the first start-up, read the operating instructions
for the operator panels.
!
The air handling unit may only be operated with the filters installed.
!
Replace the air filters with clean ones after the first few hours of operation.
!
In this manual, the mask graphics of the HMI ADVANCED operator panel are used. The masks
in other panels may differ slightly from those shown in the manual.
7.1.1
CHECKING THE CONDITION OF THE INSTALLATION
PRE-LAUNCH ACTIVITIES
Correct application of the
device
Completeness of
installation
Connection to air ducts
Condition of air ducts
Quality of installation on
site
www.vtsgroup.com
As part of the commissioning procedure, it must be checked that the air
conditioning/ventilating/heating unit in question has been constructed
and installed in accordance with the structural/installation design and
the manufacturer's guidelines.
Verify the presence of all AHU features and accessories (filters,
dampers, actuators, valves, heaters/coolers, etc.) against the technical
sheet - a full list of AHU components can be found in the technical sheet
of the AHU, as well as on the labels of the individual delivery packages.
Check that all ventilation equipment and components have been
mechanically fitted and connected to the duct system.
Check that the ducts are clean and the controls on the ducts are pre-
adjusted.
Check that the functional systems and components of the equipment
have not been damaged during assembly or other operations,
as well as Control components,
OIMM VENTUS COMPACT - ver. 6.0.0 (06.2024)
57