HVC 450 kW E-Bus Charger Installation Guide

3. Preparation

3.1. About preparation

The planning steps for the preparation phase are shown in the figure below:
A1
Ordering
Order the HVC 450 kW E-Bus Charger.
A2
Engineering
The owner / site operator selects a contractor to do the civil and electrical installation
work. The contractor is responsible for all construction documentation of the site,
among other things: drawings, calculations, certifications, licenses and test reports.
The location of the HVC 450 kW E-Bus Charger must be chosen. See section Location
on Page 26 and section Geometry of infrastructure on Page 27.
A3
Get permits
Take care of all permits and local regulations. See section Permits on Page 25.
A4
Upgrade grid
If required, upgrade the electrical grid connection to 3-phase 480 V AC. See section
Upgrade grid on Page 26.
A5
Transport foundation(s) on request
If it is necessary to order the foundation(s), the transport of the foundation(s) must be
arranged with the ABB Delivery department. See Contact information on Page 13 for
contact.