Commissioning Tm54F; Basic Sequence Of Commissioning - Siemens SINAMICS S120 Function Manual

Safety integrated
Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Commissioning

6.10 Commissioning TM54F

6.10
Commissioning TM54F
6.10.1

Basic sequence of commissioning

The following conditions must be met before you can configure the TM54F:
● Initial commissioning of all drives has been completed.
● F-DIs and F-DOs of the TM54F that are to be used must be wired.
Configuration sequence
1. Insert the TM54F
2. Configure the TM54F and generate the drive groups
3. Configure Safety functions of the drive groups
4. Configure inputs, configure outputs
5. Copy parameters to the 2nd drive object (TM54F_SL)
6. Changing the safety password
7. Activate the configuration by selecting "Activate settings"
8. Save the entire project to Startdrive
9. Save the project in the drive by selecting "Copy RAM to ROM"
10.Execute POWER ON
11.Acceptance test
Note
Commissioning TM54F
• TM54F is not yet available in Startdrive.
• You can find information on commissioning with STARTER in older editions of this
manual.
312
Function Manual, 12/2018, 6SL3097-5AR00-0BP1
Safety Integrated

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents