Port Audit and Update Test (#36)

This test sends port level translation data from the switch processor to the DS1 Interface Media Module
to assure that the trunk's translation is correct. The port audit operation verifies the consistency of the
current state of the trunk as kept in the DS1 Interface Media Module and in the switch software.
Table 55: TEST #36 Port Audit and Update Test 1 of 2
Error
Test
Code
Result
ABORT
1000
ABORT
1006
ABORT
2000
ABORT
2100
ABORT
108
Description/ Recommendation
Internal system error
Retry the command at 1-minute intervals a maximum of 5 times.
The port may be busy with a valid call.
Use display port GGGVSpp to determine the trunk group/member
number of the port. Use the status trunk command to determine the
service state of the port. If the port is in use, wait until the port is idle before
testing.
If the port status is active but the port is not in use (no calls), check the error
log for error type 1025. The port may be locked up.
If the port status is idle, retry the command at 1-minute intervals a
maximum of 5 times.
The test was aborted because the trunk is out of service.
Use status trunk to verify that the trunk is out of service.
If the trunk is out of service, determine why.
To put the trunk back in service, use the release trunk command. Retry
the test.
Response to the test was not received in the allowable time period.
Could not allocate resources to run this test.
Retry the command at 1-minute intervals a maximum of 5 times.