System Technician-Demanded Tests:
Descriptions and Error Codes
Always investigate tests in the order presented in the table below when inspecting errors in the system.
By clearing error codes associated with the NPE Crosstalk Test, for example, you may also clear errors
generated from other tests in the testing sequence.
Table 123: System Technician-Demanded Tests
Order of Investigation
NPE Crosstalk Test (#6)
Note: This Test will abort with Error Code 1412
Conference Circuit Test (#7)
Note: This Test will abort with Error Code 1412
DS1 Tie Trunk Seizure Test (#136)

Port Audit and Update Test (#36)

*D = Destructive; ND = Nondestructive
Port Audit and Update Test (#36)
This test sends port level translation data from switch processor to the DS1 Interface Media Module to
ensure that the trunk's translation is correct. Translation updates include the following data: trunk type
(in/out), dial type, timing parameters, and signaling bits enabled. The port audit operation verifies the
consistency of the current state of the trunk kept by the DS1 Interface Media Module and the switch
software.
Table 124: TEST #36 Audit and Update Test 1 of 3
Error
Test
Code
Result
ABORT
Maintenance of the Avaya G350 Media Gateway
June 2004
Avaya Communication Manager controlled maintenance
Description/ Recommendation
Internal system error
Retry the command at 1-minute intervals a maximum of 5 times.
TIE-DS1 (DS1 Tie Trunk)
Short Test
Long Test
Sequence
Sequence
X
X
X
X
X
X
D/ND*
ND
ND
ND
ND
1 of 3